Airlie Beach and Cedar Creek Amenities Upgrades

Share Airlie Beach and Cedar Creek Amenities Upgrades on Facebook Share Airlie Beach and Cedar Creek Amenities Upgrades on Twitter Share Airlie Beach and Cedar Creek Amenities Upgrades on Linkedin Email Airlie Beach and Cedar Creek Amenities Upgrades link

Consultation has concluded

We are undertaking works to amenities blocks at the Airlie Beach Lagoon, Cedar Creek Falls and Brandy Creek at the Great Whitsunday Walk Entrance.

Works may create impacts to residents, nearby businesses, tour operators and visitors. Below is a quick overview of each project and anticipated impacts.

ProjectTimingProject overview
Airlie Beach Lagoon Amenities
(see fact sheet)
9 October - 15 December
  • The amenities upgrade will be closed in 2 stages to refurbish and repaint the facility from 9 October - 4 December (8 weeks).
  • Works will include new pavements, new shower, refurbished toilets, new water drinking facilities, increased change room size, upgraded disabled toilet and parent room facilities.
  • A temporary amenities block with parent facilities and disabled portaloo will be provided during construction.
  • Majority of the facilities (stage 1) will be re-opened after a month of work.
Cedar Creek Falls Amenities
(see fact sheet)

Complete
Car park re-seal to occur 2024
  • Construction will commence to create a new amenities block and car parking from 2 October - late October, subject to weather.
  • Works include the creation of a new amenities block and decommissioning of the old amenities block, which will be replaced with 13 additional car parks.
  • The existing amenities block will remain open until the new amenities block is completed. Once the new amenities block is open, works will commence to decommission the old amenities and cut / retain the site for the creation of 13 new car parks.
  • Works are supported by the Queensland Government's Works for Queensland Grant Program.
Brandy Creek AmenitiesComplete
  • Please also be aware that we are creating new amenities at the Brandy Creek Great Whitsunday Walk entrance. Works will commence from 27 September to early October.
  • Currently no facilities exist to service the Great Whitsunday Walk, so this will benefit users and events, such as Whitsunday Trailfest.
  • Construction will not impact users.
  • Works are supported by the Queensland Government's Works for Queensland Grant Program.


If you have any concerns regarding the above works, prior to or during construction, please don't hesitate to notify us via the survey link below. If it is urgent please email: info@whitsundayrc.qld.gov.au or Phone: 1300 972 753.

We apologise for the inconvenience of the works to residents, visitors and business owners.

We are undertaking works to amenities blocks at the Airlie Beach Lagoon, Cedar Creek Falls and Brandy Creek at the Great Whitsunday Walk Entrance.

Works may create impacts to residents, nearby businesses, tour operators and visitors. Below is a quick overview of each project and anticipated impacts.

ProjectTimingProject overview
Airlie Beach Lagoon Amenities
(see fact sheet)
9 October - 15 December
  • The amenities upgrade will be closed in 2 stages to refurbish and repaint the facility from 9 October - 4 December (8 weeks).
  • Works will include new pavements, new shower, refurbished toilets, new water drinking facilities, increased change room size, upgraded disabled toilet and parent room facilities.
  • A temporary amenities block with parent facilities and disabled portaloo will be provided during construction.
  • Majority of the facilities (stage 1) will be re-opened after a month of work.
Cedar Creek Falls Amenities
(see fact sheet)

Complete
Car park re-seal to occur 2024
  • Construction will commence to create a new amenities block and car parking from 2 October - late October, subject to weather.
  • Works include the creation of a new amenities block and decommissioning of the old amenities block, which will be replaced with 13 additional car parks.
  • The existing amenities block will remain open until the new amenities block is completed. Once the new amenities block is open, works will commence to decommission the old amenities and cut / retain the site for the creation of 13 new car parks.
  • Works are supported by the Queensland Government's Works for Queensland Grant Program.
Brandy Creek AmenitiesComplete
  • Please also be aware that we are creating new amenities at the Brandy Creek Great Whitsunday Walk entrance. Works will commence from 27 September to early October.
  • Currently no facilities exist to service the Great Whitsunday Walk, so this will benefit users and events, such as Whitsunday Trailfest.
  • Construction will not impact users.
  • Works are supported by the Queensland Government's Works for Queensland Grant Program.


If you have any concerns regarding the above works, prior to or during construction, please don't hesitate to notify us via the survey link below. If it is urgent please email: info@whitsundayrc.qld.gov.au or Phone: 1300 972 753.

We apologise for the inconvenience of the works to residents, visitors and business owners.